Schedule
Phase 1
- Route studies, field surveys and design began in 2021
- CPCN application filed in April 2022
- Permitting and land acquisition 2022
- Construction 2023
- Restoration 2023-2024
Phase 2
- Route studies, field surveys and design 2022
- Permitting and land acquisition 2023
- Construction 2024
- Restoration 2025
Phases 3-5
- To be completed at a later time