Rattler Solar Center

Rattler Solar Center

Hernando County

At Duke Energy, we believe generating electricity from renewable resources will play an important role in the transition to cleaner energy. That's why we're developing innovative renewable power projects to serve communities and help strengthen the energy system. 

Duke Energy has been harnessing the power of the sun and advancing solar technologies in Florida since the late 1980s. The company currently operates more than 20 solar power facilities in Florida with plans to add several additional facilities in 2024 and 2025. 

Project Description

The new Rattler Solar Center will be constructed in Hernando County using photovoltaic (PV) panels, a proven technology that converts sunlight into electricity. These panels will effectively produce enough electricity to power about 23,000 average-sized homes at peak production. 

Project Details 

  • Located at 27590 Lake Lindsey Road, Brooksville, in Hernando County. 
  • Fenced-in area of the project is 560 acres located on a 2,100-acre parcel. 
  • 74.9-megawatt (MW) facility. 
  • Approximately 210,000 solar panels.

Preliminary Site Plan

Aerial view of the Rattler Solar Center site.

A vegetation buffer around the facility has been incorporated into the design to minimize visual impacts. The facility will operate safely, quietly and reliably for approximately 30 years.

Benefits to the Community 

  • Increase energy capacity to help provide safe and reliable energy to homes, businesses and community facilities now and in the future. 
  • During the nine- to 12-month construction period, the project will have up to 220 workers on-site at the peak of construction.
  • Project workers will support the local economy by frequenting businesses, restaurants and hotels. 
  • The project will increase tax revenue for Hernando County and other local taxing authorities, which may provide resources for public services and initiatives.

Operational Features

  • Safe, quiet generation 
  • No air emissions or waste production 
  • Minimal water needs 
  • Minimal impact on local traffic 
icon hourglass

Timeline

  • Mid-to-late 2024

    Permitting

  • Early 2025

    Site preparation and solar installations

  • Late 2025

    Center operational

What to Expect During Construction

  • Increased traffic from equipment and working vehicles.
  • Vegetation clearing and grading of the site.
  • Normal construction noise.
  • Crews working weekdays during daylight hours, with some limited weekend work possible.

Maintenance and Operation After Construction

  • The facility will primarily be operated remotely from a dedicated solar service center.
  • Periodic inspections, mowing and routine maintenance will be performed each month. 