Williston North to Martin West

Project At a Glance

Project:Replace 60 H-frame structures with steel monopoles (single poles)
Project area: Marion County, city of Ocala, Levy County, town of Williston
Project plan: Rebuild existing transmission line 
Line length to be rebuilt: 14.1 miles
End point: Williston North Substation (4991 Northeast Highway 41)
End Point: Martin West Substation (10460 NW Gainesville Road)
 

Project Location

Route Map Martin West Segment

View larger map

H-frame structures will be replaced with stronger steel monopole structures which will require less maintenance, have a smaller footprint, and be more resilient against severe weather conditions.

The work will take place within existing Duke Energy easement areas.

Before and after photos of the transmission structures.
The new steel structures as shown on the right above may not be this exact design. This photograph represents a typical steel monopole configuration.

Timeline*

  • Preconstruction work, including surveying, soil boring and staking

    Fall 2021

  • Vegetation removal

    Winter 2022

  • Transmission line construction

    Spring 2023

  • Project completion

    Summer 2024

*Timeline is subject to change based on permitting timelines, additional scope development, weather conditions or other uncontrollable events. Factors such as weather, availability of crews and equipment or unforeseen circumstances may impact the schedule. Many of the activities associated with the design, engineering, and construction of the transmission lines may overlap and do not necessarily happen in a sequential manner. These activities will occur in different locations at different times based on the size of the project and need to optimize the use of resources.

Helpful Videos to Learn More

Learn more about the importance of transmission and how it plays a vital role in powering our communities.
icon question

Frequently Asked Questions

Image

Contact Us

Additional Resources